[EXPIRED] Roadworks, roadworks, roadworks
Christchurch BID via Facebook - on 12th June - provided the following update for the ongoing roadwork chaos around the Police Station site housing development:
Following a meeting this morning with Christchurch & District Chamber, Christchurch BID and BCP the revised development works for the former Police station in Christchurch are as follows.
Presently (12/06/26) to Friday 26 June 2026 One lane outbound towards Bournemouth on Barrack Road closed
Tuesday 16 June 2026 one inbound and one outbound lane closures – 2-way free flow traffic maintained on Barrack Road
On Friday 26 June 2026 all works cleared off Barrack Road.
Bargates full closure 29 June to 17 July 2026 for new pedestrian crossing to the development on northern arm of roundabout.
Fountain roundabout night time resurfacing works postponed until early September (date to be agreed).
Published: 20th June 2026; expired: 17th July 2026 23:59:59